Duplex Project
Header image
Home, Septic, & Well Inspections
  [ HOME ]  
 
 
Recent photos of Westrent Park Apartments under construction
small product photo   small product photo    
12-04-06 Concrete form in place   12-04-06  Pad built and footings dug   1-10-07 Main slab poured porches being formed  
 
     
2-5-07 Framing begins   2-12-07 Framing progress   4-09-07 Fire wall installed between units, framing begins on second half  
 
   

 
5-24-07 Framing progress, or lack thereof   6-25-07 Framing complete, wrap and windows started   8-1-07 Siding nearly complete, trim not yet installed  

Time Line (actual):

November 07, 2006: Drawings completed

November 09, 2006: Building permit obtained

November 20, 2006: Pad completed

December 04, 2006: Rough plumbing begins             

December 14, 2006 Passed plumbing inspection

January 12, 2007 Concrete work complete

February 5, 2007 Framing begins

June 25, 2007 Framing complete, plumbing begins

             
       
  8-1-07 front view   8-1-07 stairway 8-1-07 view of balcony from below