Time Line (actual):
November 07, 2006: Drawings completed
November 09, 2006: Building permit obtained
November 20, 2006: Pad completed
December 04, 2006: Rough plumbing begins
December 14, 2006 Passed plumbing inspection
January 12, 2007 Concrete work complete
February 5, 2007 Framing begins
June 25, 2007 Framing complete, plumbing begins |